The project, situated on 30 acres of privately owned farmland, utilizes single-axis tracking technology designed to maximize output by following the sun’s path. While the site will not feature battery storage, the facility is engineered to feed power directly into the local distribution grid. Lightstar intends to prioritize local labor, employing regional installers and electricians throughout the construction phase.
Senior Development Manager Kyle McAdam emphasized that the site underwent rigorous environmental vetting before breaking ground. Studies included a Phase I Environmental Site Assessment and historical resource surveys, which yielded no findings. A identified wetland area on the property has been incorporated into the project design to ensure its preservation. Upon the facility’s eventual decommissioning, Lightstar is committed to removing all infrastructure, allowing the land to return to its original agricultural purpose.